Current Report No. 2/2020

30.01.2020 18:40

Information update on the construction of the power generating unit at Jaworzno

In reference to the current report no. 57/2019 of December 19, 2019, TAURON Polska Energia S.A. (”Issuer”) announces that on January 30, 2020 it received from Nowe Jaworzno Grupa TAURON sp.z o.o. ("NJGT") information on the change of the commissioning date of of the 910 MWe supercritical power generating unit at Jaworzno III Power Plant - Power Plant II ("Unit").

Unit contractor i.e. Consortium RAFAKO S.A. and MOSTOSTAL WARSZAWA S.A. (”Consortium”) notified NJGT that the Unit will be ready for commissioning on February 4, 2020. Considering the information received from the Consortium, NJGT conducted an internal analysis checking the Unit construction schedule. Taking into account technical tests and trial operation of the Unit conducted so far, NJGT estimates that the final commissioning of the Unit should take place by February 15, 2020.

The Issuer holds 84.76 percent votes and shares in NJGT.

Art. 17, clause 1 of MAR – inside information.
 