Skip Ribbon Commands
Skip to main content
This site uses cookie files. Using this site means, that you accept the use of cookies, according to your web browser settings. You can change those settings anytime. Details can be found in our Cookie Policy.
 
 
 
 

Current reports

Publications:

Current Report No. 11/2020

23.03.2020
Signing of the memorandum of understanding on the preliminary terms of cooperation between TAURON and PFR with respect to investments in renewable energy sources
​TAURON Polska Energia S.A. ("TAURON") announces that on March 23, 2020 a memorandum of understanding was signed between TAURON and closed-end investment funds, a part of whose investment portfolio is managed by Polski Fundusz Rozwoju S.A. (Polish Development Fund) ("PFR"), which sets out the preliminary terms of cooperation under consideration...

Current Report No. 10/2020

19.03.2020
TAURON Polska Energia Capital Group’s estimated results for 2019 and Q4 2019
TAURON Polska Energia S.A. (“Company”, “Issuer”) presents selected estimated consolidated financial results and operating data of TAURON Polska Energia S.A. Capital Group (“TAURON Group”, “Group”) for 2019 and Q4 2019. Selected estimated financial results for: (a) 2019 Sales revenue and compensations: PLN 20,511 million EBITDA (operating...

Current Report No. 9/2020

17.03.2020
Update of the impairment tests results
In reference to current report no. 5/2020 of March 4, 2020, TAURON Polska Energia S.A. ("Issuer") announces that in connection with the extension of the 910 MW unit in Jaworzno commissioning date (current report no. 7/2020 of March 6, 2020), additional analyses were carried out as part of impairment tests of assets. The analyses completed...

Current Report No. 8/2020

16.03.2020
Signing of the loan agreement with SMBC BANK EU AG
TAURON Polska Energia S.A. (”Issuer") announces that, on March 16, 2020, it concluded a loan agreement with SMBC BANK EU AG worth PLN 500 million ("Loan Agreement”), the proceeds from which may be used to cover the Issuer’s general corporate purposes, but excluding construction, acquisition, extension of any coal fired power plants and refinancing...

Current Report No. 7/2020

06.03.2020
Update of information on the construction of the power generating unit in Jaworzno
In reference to the current report no. 4/2020 of February 13, 2020, TAURON Polska Energia S.A. ("Issuer") informs that on March 6, 2020 Nowe Jaworzno Grupa TAURON sp. z o.o. ("NJGT") received a statement from RAFAKO S.A. regarding the estimated date of commissioning of the 910 MWe power generating unit in Jaworzno (“Unit”). RAFAKO S.A....

Current Report No. 6/2020

06.03.2020
Ruling of the Regional Court related to Polska Energia - Pierwsza Kompania Handlowa sp. z o.o.
In reference to current report No. 7/2015 of March 19, 2015 on the termination of contracts for purchase of electricity and property rights by a subsidiary, the Management Board of TAURON Polska Energia S.A. (”Issuer”) informs that on March 6, 2020 the Regional Court in Gdańsk (”Court”) issued a partial and preliminary ruling in the lawsuit...

Current Report No. 5/2020

04.03.2020
Impairment test results
TAURON Polska Energia S.A. (”Issuer”, ”TAURON”) announces that the main analyses conducted as part of the impairment tests related to TAURON Capital Group’s assets carrying amount as of December 31, 2019, were completed on March 4, 2020. The analyses demonstrated material changes to the recoverable carrying value of the Generation and...

Current Report No. 4/2020

13.02.2020
Update of information on the construction of the power generating unit at Jaworzno
In reference to the current report no. 2/2020 of January 30, 2020, TAURON Polska Energia S.A. ("Issuer") announces that it received information that on February 13, 2020 Nowe Jaworzno Grupa TAURON sp.z o.o. ("NJGT") received a statement from the company E003B7 sp.z o.o. (a subsidiary of RAFAKO SA, "E003B7") in which E003B7 in particular indicates...

Current Report No. 3/2020

06.02.2020
Bond issue program established
TAURON Polska Energia S.A. (”Issuer") informs that on February 6, 2020, it concluded, with Santander Bank Polska S.A. (”Bank”), a program agreement (”Program Agreement”), pursuant to which a bond issue program (”Program”). Within the Program the Issuer has the option of issuing bonds up to a maximum PLN 2 billion, with the value of the...

Current Report No. 2/2020

30.01.2020
Information update on the construction of the power generating unit at Jaworzno
In reference to the current report no. 57/2019 of December 19, 2019, TAURON Polska Energia S.A. (”Issuer”) announces that on January 30, 2020 it received from Nowe Jaworzno Grupa TAURON sp.z o.o. ("NJGT") information on the change of the commissioning date of of the 910 MWe supercritical power generating unit at Jaworzno III Power Plant -...